Birmingham Dental Hospital Site Options & Feasibility Study

Brief
To review existing and new site options within the vicinity of University of Birmingham. Working collectively the health planning and design teams were to guide stakeholders through the site selection process and once concluded to prepare a site specific design brief to RIBA stage B.

Client: NHS South Birmingham / South Birmingham Community Health

Location: South Birmingham

Timescales: 4 months

Briefed: December 2009
Site Selection: March 2010

Solution
The BaS LIFT Team identified three feasible site options, which when considered in conjunction with financial and timescale issues led to a preferred option. This enabled engagement with landowners and the planning authority with a view to delivering a developable site in due course.

Challenges
Tight timescale and liaising with a broad range of stakeholders with differing requirements.

Services
Development, Design (Architecture) and Design Brief

Top of page | Back